* The processing of connection requests to the national electricity grid by the system operators will, however, be subject to the completion of integration studies in accordance with the legal and regulatory provisions in force.
Heatmap
DSO
Capacity (MW)
SRM CASA-SETTAT
375,00
SRM SOUSS-MASSA
84,00
SRM MARRAKECH-SAFI
109,00
SRM L'ORIENTAL
60,00
SRM DRAA-TAFILALET
32,00
SRM FES-MEKNES
152,00
SRM FES-MEKNES RESERVED
33,00
SRM LAAYOUNE-SAKIA EL HAMRA
30,00
SRM BENI MELLAL-KHENIFRA
57,00
SRM DAKHLA-OUED EDDAHAB
17,00
SRM GUELMIM-OUED NOUN
23,00
SRM TANGER-TETOUAN-AL HOCEIMA
60,00
AMENDIS
96,00
AMENDIS RESERVED
35,00
SRM RABAT-SALE-KÉNITRA
86,00
REDAL
143,00
Total Hosting Capacity
1324,00
Hosting Capacity reserved by the free market:
68,00
Total Capacity (MW)
CASA-SETTAT
2026
196,00
2027
248,00
2028
262,00
2029
375,00
2030
375,00
SOUSS-MASSA
2026
37,00
2027
47,00
2028
50,00
2029
84,00
2030
84,00
MARRAKECH-SAFI
2026
57,00
2027
72,00
2028
76,00
2029
109,00
2030
109,00
L'ORIENTAL
2026
32,00
2027
39,00
2028
42,00
2029
60,00
2030
60,00
DRAA-TAFILALET
2026
18,00
2027
22,00
2028
23,00
2029
32,00
2030
32,00
FES-MEKNES
2026
64,00
2027
89,00
2028
95,00
2029
152,00
2030
152,00
LAAYOUNE-SAKIA EL HAMRA
2026
17,00
2027
18,00
2028
18,00
2029
30,00
2030
30,00
BENI MELLAL-KHENIFRA
2026
28,00
2027
37,00
2028
40,00
2029
57,00
2030
57,00
DAKHLA-OUED EDDAHAB
2026
10,00
2027
10,00
2028
10,00
2029
17,00
2030
17,00
GUELMIM-OUED NOUN
2026
13,00
2027
14,00
2028
14,00
2029
23,00
2030
23,00
TANGER-TETOUAN-AL HOCEIMA
2026
100,00
2027
126,00
2028
134,00
2029
156,00
2030
156,00
RABAT-SALE-KÉNITRA
2026
119,00
2027
149,00
2028
160,00
2029
229,00
2030
229,00